Heet Hospital Operating Rooms Project

7 ISO Class 5 / Class 7 operating rooms for a 400-bed hospital, completed in just 1.5 months in 2026 as the second phase of the same healthcare program — interlocked entrance, hermetic doors, 2400x2400 mm laminar ceiling with H14 HEPA filtration.

Heet, Anbar, IraqMedical / Hospital
Location
Heet, Anbar, Iraq
Completed
In 1.5 months, 2026
Industry
Medical / Hospital
Application
Operating Rooms
Size
1,280 m²
OR Classification
ISO 14644-1 Class 5 (LAF Zone) / Class 7 (Operating Room)
Heet Hospital Operating Rooms Project - 1
Heet Hospital Operating Rooms Project - 2
Heet Hospital Operating Rooms Project - 3
Heet Hospital Operating Rooms Project - 4
Heet Hospital Operating Rooms Project - 5
1 / 5

Project Scope

The operating rooms of a 400-bed hospital were designed and built in just 1.5 months in 2026. There are 7 operating rooms in total in this area with an interlocked entrance, all classified as ISO 14644-1 Class 5 / Class 7. As the second phase of the same operating room program following the Haditha project, it was completed faster thanks to the experience gained from the first phase.

Hermetic Door Systems

The doors of Operating Rooms are touch-free hermetic system which prevents air-leakage.

  • Touch-Free Hermetic Doors
  • Air-Leakage Prevention
  • Interlocked Entrance System

Laminar Ceiling & HEPA Filtration

There are 2400x2400 mm laminar ceiling with H14 HEPA filter at the center of each room to maintain laminar flow requirement during the operations.

  • 2400x2400 mm Laminar Ceiling
  • H14 HEPA Filter
  • Laminar Flow During Operations

Return Air Grilles

SS304 low and high return grilles are located both top and the bottom of the 45° corner to prevent any dirty air accumulation inside the room.

  • SS304 Return Grilles
  • 45° Corner Mounting
  • Low and High Position